Santo Domingo.– The parallel load test of the train was successful, after the unit traveled the entire planned route, reached the maneuvering tail and the track changes were made according to the established technical protocol.
The test is part of the operational evaluations prior to the commissioning of the extension of Line 2-C of the Santo Domingo Metro, which will connect Los Alcarrizos with kilometer 9 of the Duarte highway.
You may be interested in: Metro stations close their doors for "Christmas Eve"
During the day, the performance of the railway system, the synchronization of the rails, the track changes, and the train's responsiveness under conditions similar to real operation were verified. These tests are part of the validation process to ensure the security, efficiency, and reliability of the service before its official opening, announced by President Luis Abinader for February 24th. The new extension is expected to positively impact urban mobility by integrating thousands of users from the municipality of Los Alcarrizos into the mass transit system.